PROJECTS
2014 – Steam Turbine Generator Piping
Pipe Fabrication and Installation
-
Mechanical installations (agitators, pumps, motors and vessels)
-
Major structural prefabrication and installation
-
Hired structual contractor
-
X-ray and hydro testing
-
Commissioning
Project Duration: 9 Months
2016 – City of Prince George Wastewater Treatment Plant
-
Pre-fabrication of stainless steel piping
-
Onsite changeout of skum skimmers
-
Installation of trickle filter piping
-
Installation of overhead crane
Project Duration: 6 Months
​
2016 – Shut Down Work for Hydroelectric Dam
Completed work for a scheduled shut down as well as installing new lines improve functionality of the project as a whole
-
Installation of pipe
-
Major structural prefabrication and installation
-
Commissioning of work
Project Duration: 2 Months